Isaca- CISA
| Question ID 22457 |
A team conducting a risk analysis is having difficulty projecting the financial losses that could result from a risk. To evaluate the potential losses, the team should: |
| Option A |
compute the amortization of the related assets. |
| Option B |
calculate a return on investment (ROI). |
| Option C |
apply a qualitative approach. |
| Option D |
spend the time needed to define exactly the loss amount. |
| Correct Answer | C |
Update Date and Time 2018-03-30 05:19:28
| Question ID 22490 |
Before implementing an IT balanced scorecard, an organization must: |
| Option A |
deliver effective and efficient services. |
| Option B |
define key performance indicators. |
| Option C |
provide business value to IT projects. |
| Option D |
control IT expenses. |
| Correct Answer | B |
Description A definition of key performance indicators is required before implementing an IT balanced scorecard. Choices A, C and D are objectives.
Update Date and Time 2018-04-03 06:30:53